March Construction Update

The Lower Mainland certainly experienced a strong bout of snow this February – but construction at the Houses continued where possible!   We are down to the last stretch of Phase 7 Houses, with only 4 more Houses in that phase left to turnover.  In Phase 8, many Houses on the south end have siding installation occurring, and we are working on the roofing and rough in plumbing for the Houses on the north end.   
Over at Phase 9, 50% of the Houses have had their foundations poured, while the remaining 50% have underground site servicing in progress. 

mar con

 

mar con 1

A forklift stationed near the Phase 8 Houses, where siding is making progress on the Houses furthest south.

mar con 2

 An image of the next house to receive a walk through – we are very excited for the homeowner to see their beautiful floor plan and Birch colour schemed home (one of our most popular colour schemes on site)!


Share this News item

Return to the News