March Construction Update
The Lower Mainland certainly experienced a strong bout of snow this February – but construction at the Houses continued where possible! We are down to the last stretch of Phase 7 Houses, with only 4 more Houses in that phase left to turnover. In Phase 8, many Houses on the south end have siding installation occurring, and we are working on the roofing and rough in plumbing for the Houses on the north end.
Over at Phase 9, 50% of the Houses have had their foundations poured, while the remaining 50% have underground site servicing in progress.