February Construction Update
The exterior on three sides of the Phase 4 Condo building is finished. The south side of the building is 90% complete, and landscaping is in progress.
Final patching is happening on the fourth floor corridors. The finishing’s from the fourth floor to second floor are near complete, and we have a large crew focusing on the first floor to install the outstanding finishing’s before beginning the final patchwork.
We have begun framing the last House in Phase 8, having good weather definitely helps us during construction.