As many visitors and Homeowners can see, our work at the Phase 3 Condo has progressed up to the sixth floor West now where walls are being formed! The masonry for our underground parkade is 80% complete. We are also 100% complete for interior framing on the first and second floor, and 100% complete for exterior framing on the third floor.
The unusually heavy bout of Lower Mainland snow during the last month did not stop our crews from working day and night on our scheduled concrete pour (on one of the heaviest snow days!), and we are very proud of the efforts that our trades and construction team have demonstrated throughout the challenging weather. It was a successful pour. Please see below for photos of the work that progressed throughout the snowfall!