Half of Phase 5 is now complete. All houses have their roofs on, and siding is about to be installed on the last house.  In the second half of Phase 5, we are installing cabinets, and drywall. Wiring and insulation in the last two houses are in progress. Landscaping is in effect, and will be finished after the interior of houses are completed. In Phase 6, we have installed two roofs. All of the north side houses have been roughed-in, and seven of them have been framed.