Construction Update
Condo Construction Update
In early February, we began drilling the boreholes for the Geo-Exchange System at our Phase 3 Condo! The boreholes go 240 feet below ground, and we will be drilling 88 of them. As of this week, we’ve already completed 21 boreholes. Please see below for our progress photos, as well as a mock-up image of the size and space of our upcoming Condo: 5011 Springs Boulevard.