Construction Update
We have began our concrete pours at our Phase 4 Condo, 4977 Springs Boulevard! We started with the raft slab two weeks ago, which is the ground level at the underground parkade. The work began at 7 am and went until 4 pm, where upon we completed 11,662 square feet on the west end of the building! Our second successful pour occurred yesterday for the walls of that first section in the underground. The upcoming pour will be for the second section of the raft slab, where we are planning on completing the next 15, 378 square feet of the underground. Please see below for photos!